Kynachan

Kynachan is a storage project of 300 MW in NESO's TEC Register of 23 Oct 2026, connecting at Kynachan BESS 132kV Substation (SHET). Status: Scoping. Gate 1.

Customer
Geocore Ltd
Connection site
Kynachan BESS 132kV Substation
Transmission owner
SHET
Technology
Storage
Capacity (TEC)
300 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2035
NESO project number
PRO-003502