Knarie
Knarie is a storage, onshore wind project of 297 MW in NESO's TEC Register of 23 Oct 2026, connecting at Narie 400/132kV Substation (SPT). Status: Awaiting Consents. Gate 1.
- Customer
- Invenergy Development UK Ltd
- Connection site
- Narie 400/132kV Substation
- Transmission owner
- SPT
- Technology
- Storage, Onshore wind
- Capacity (TEC)
- 297 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Awaiting Consents
- MW effective from
- 31 Oct 2036
- NESO project number
- PRO-004048
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.