Kellwood Road BESS

Kellwood Road BESS is a storage project of 40 MW in NESO's TEC Register of 23 Oct 2026, connecting at Dumfries 132/33kV (SPT). Status: Consents Approved. Gate 2.

Customer
Geocore (Kellwood) Ltd
Connection site
Dumfries 132/33kV
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
40 MW
Agreement
Embedded
Gate
Gate 2
Status
Consents Approved
MW effective from
30 Jul 2030
NESO project number
PRO-003710

Also at Dumfries 132/33kV

ProjectTechnologyMW
DalswintonOnshore wind30
Mosspark Energy ParkStorage, Solar50