Grid GuardianOpen the evidence in the app

J102A Oldbury BESS

J102A Oldbury BESS is a storage project of 99.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Severn Connection Node A 132kV Substation (NGET). Status: Scoping. Gate 1.

Customer
RWE Renewables UK Solar and Storage Limited
Connection site
Severn Connection Node A 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
99.9 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-003784

Also at Severn Connection Node A 132kV Substation

ProjectTechnologyMW
Barry Road StorageStorage110
Care Power Berkeley BEGAStorage49.9
KX Alpha 1 Iron ActonStorage99
KX Alpha 2 Iron ActonStorage99
KX Alpha 3 Iron ActonStorage99.9
Lightsource Folly FarmStorage, Onshore wind240
Stockhills FarmStorage, Solar, Onshore wind800