Hunterston PARC BESS
Hunterston PARC BESS is a storage project of 250 MW in NESO's TEC Register of 23 Oct 2026, connecting at Hunterston 400/132kV (SPT). Status: Scoping.
- Customer
- PULSE CLEAN ENERGY LIMITED
- Connection site
- Hunterston 400/132kV
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 250 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 31 Oct 2033
- NESO project number
- PRO-003865
Also at Hunterston 400/132kV
| Project | Technology | MW |
|---|---|---|
| Hunterston | Nuclear | 0 |
| Hunterston Hydrogen | Hydrogen | 5 |
| Hunterston Wind Farm | Storage, Onshore wind | 70 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.