Grid GuardianOpen the evidence in the app

Hunterston Battery Storage Facility

Hunterston Battery Storage Facility is a storage, reactive compensation project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Hunterston East 400kV substation (SPT). Status: Consents Approved. Gate 2.

Customer
HUNTERSTON GRID 1 LTD
Connection site
Hunterston East 400kV substation
Transmission owner
SPT
Technology
Storage, Reactive Compensation
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Consents Approved
MW effective from
10 Mar 2028
NESO project number
PRO-001155

Also at Hunterston East 400kV substation

ProjectTechnologyMW
Highview Hunterston East CryobatteryDemand, Storage, Reactive Compensation200

Source