Hinkley Point C
Hinkley Point C is a nuclear project of 1,670–3,340 MW in NESO's TEC Register of 23 Oct 2026, connecting at Shurton 400kV Substation (NGET). Status: Scoping.
- Customer
- NNB GENERATION COMPANY (HPC) LIMITED
- Connection site
- Shurton 400kV Substation
- Transmission owner
- NGET
- Technology
- Nuclear
- Capacity (TEC)
- 1,670–3,340 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 31 Mar 2029, 31 Jul 2030
- NESO project number
- PRO-001674-1, PRO-001674-2
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.