Grovers Farm BESS

Grovers Farm BESS is a storage project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at West London Connection Node B 132kV substation (NGET). Status: Scoping. Gate 1.

Customer
Bluestone Energy Ltd
Connection site
West London Connection Node B 132kV substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
240 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-003196

Also at West London Connection Node B 132kV substation

ProjectTechnologyMW
Brentford (SSEN-FBT624) -120MW BESSStorage120