Grid GuardianOpen the evidence in the app

Green Frog @ Rake Lane

Green Frog @ Rake Lane is a gas project of 21 MW in NESO's TEC Register of 23 Oct 2026, connecting at Kearsley 132kV substation (NGET). Status: Built.

Customer
VIRIDIS 178 LIMITED
Connection site
Kearsley 132kV substation
Transmission owner
NGET
Technology
Gas
Capacity (TEC)
21 MW
Agreement
Embedded
Status
Built
NESO project number
PRO-001267

Also at Kearsley 132kV substation

ProjectTechnologyMW
KearsleyDemand, Storage49.9
Kearsley North Green Energy CentreDemand, Storage, Solar400

Source