Green Frog @ Down Barn Farm

Green Frog @ Down Barn Farm is a gas project of 20 MW in NESO's TEC Register of 23 Oct 2026, connecting at Lovedean 400kV Substation (NGET). Status: Built.

Customer
VIRIDIS 178 LIMITED
Connection site
Lovedean 400kV Substation
Transmission owner
NGET
Technology
Gas
Capacity (TEC)
20 MW
Agreement
Embedded
Status
Built
NESO project number
PRO-001261

Also at Lovedean 400kV Substation

ProjectTechnologyMW
EcoLovedeanStorage249
Lovedean (Tertiary)Storage, Solar57
Lovedean Greener Grid ParkStorage, Reactive Compensation49.9
Peak Gen HavantOil & AGT (Advanced Gas Turbine)21