Green Frog @ Down Barn Farm
Green Frog @ Down Barn Farm is a gas project of 20 MW in NESO's TEC Register of 23 Oct 2026, connecting at Lovedean 400kV Substation (NGET). Status: Built.
- Customer
- VIRIDIS 178 LIMITED
- Connection site
- Lovedean 400kV Substation
- Transmission owner
- NGET
- Technology
- Gas
- Capacity (TEC)
- 20 MW
- Agreement
- Embedded
- Status
- Built
- NESO project number
- PRO-001261
Also at Lovedean 400kV Substation
| Project | Technology | MW |
|---|---|---|
| EcoLovedean | Storage | 249 |
| Lovedean (Tertiary) | Storage, Solar | 57 |
| Lovedean Greener Grid Park | Storage, Reactive Compensation | 49.9 |
| Peak Gen Havant | Oil & AGT (Advanced Gas Turbine) | 21 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.