Grid GuardianOpen the evidence in the app

Glenrothes BESS

Glenrothes BESS is a storage project of 46 MW in NESO's TEC Register of 23 Oct 2026, connecting at Glenrothes 275/33kV (SPT). Status: Consents Approved. Gate 2.

Customer
GLENROTHES BESS LTD
Connection site
Glenrothes 275/33kV
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
46 MW
Agreement
Embedded
Gate
Gate 2
Status
Consents Approved
MW effective from
30 Oct 2025
NESO project number
PRO-002089

Also at Glenrothes 275/33kV

ProjectTechnologyMW
Markinch (Rothes) Biomass CHP PlantBioenergy55
Roaring Hill Energy Storage FacilityStorage49.99