Gastard BESS
Gastard BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Melksham B 132KV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- SIRIUSECODEV (GASTARD) LTD
- Connection site
- Melksham B 132KV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 200 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 15 Nov 2037
- NESO project number
- PRO-003552
Also at Melksham B 132KV Substation
| Project | Technology | MW |
|---|---|---|
| Beanacre BESS | Storage | 200 |
| Norrington Gate | Storage | 150 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.