Garlogie B-2

Garlogie B-2 is a storage, solar project of 50 MW in NESO's TEC Register of 23 Oct 2026, connecting at Garlogie Production B 275/33kV GSP (SHET). Status: Scoping. Gate 1.

Customer
GARLOGIE ENERGY CENTRE LIMITED
Connection site
Garlogie Production B 275/33kV GSP
Transmission owner
SHET
Technology
Storage, Solar
Capacity (TEC)
50 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-004641

Also at Garlogie Production B 275/33kV GSP

ProjectTechnologyMW
Garlogie B-1Storage, Solar50