Galloper Wind Farm

Galloper Wind Farm is a offshore wind project of 348 MW in NESO's TEC Register of 23 Oct 2026, connecting at Galloper North 132/33kV Substation (NGET). Status: Built.

Customer
GALLOPER WIND FARM LIMITED
Connection site
Galloper North 132/33kV Substation
Transmission owner
NGET
Technology
Offshore wind
Capacity (TEC)
348 MW
Agreement
Direct Connection
Status
Built
NESO project number
PRO-000162