Galileo 10
Galileo 10 is a storage project of 60 MW in NESO's TEC Register of 23 Oct 2026, connecting at Armadale 132kV Substation (SPT). Status: Scoping.
- Customer
- GALILEO 10 LIMITED
- Connection site
- Armadale 132kV Substation
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 60 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 31 Oct 2031
- NESO project number
- PRO-003953