Grid GuardianOpen the evidence in the app

Fort Augustus BESS

Fort Augustus BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Fort Augustus 400kV (SHET). Status: Scoping. Gate 1.

Customer
FIELD DEVCO LTD
Connection site
Fort Augustus 400kV
Transmission owner
SHET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2035
NESO project number
PRO-004599

Also at Fort Augustus 400kV

ProjectTechnologyMW
GlendoeHydro99.9

Source