Flemyland Battery Storage

Flemyland Battery Storage is a storage project of 100 MW in NESO's TEC Register of 23 Oct 2026, connecting at Kilwinning 132/33kV (SPT). Status: Consents Approved. Gate 2.

Customer
Flemyland Battery Storage Limited
Connection site
Kilwinning 132/33kV
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
100 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Consents Approved
MW effective from
27 Apr 2029
NESO project number
PRO-002360

Also at Kilwinning 132/33kV

ProjectTechnologyMW
Ardoch Farm Battery StorageStorage27
Benthead SolarStorage, Solar63