Exeter Main
Exeter Main is a storage, solar project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Exeter 400kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- ENSO GREEN HOLDINGS X LIMITED
- Connection site
- Exeter 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 400 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 28 Oct 2033
- NESO project number
- PRO-002082
Also at Exeter 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Exeter (Tertiary) | Storage, Solar | 49.9–57 |
| Exeter BESS | Storage | 290–680 |
| Exeter Main Tertiary | Thermal | 57 |
| Peak Gen Makro Exeter | Reactive Compensation | 20 |
| Tale Lane Solar / A008 Langford | Storage, Solar | 35 |
| Water Lane | CHP (Combined Heat and Power) | 20.88 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.