Grid GuardianOpen the evidence in the app

Errochty

Errochty is a hydro project of 75 MW in NESO's TEC Register of 23 Oct 2026, connecting at Errochty 132kV Substation (SHET). Status: Built.

Customer
SSE GENERATION LIMITED
Connection site
Errochty 132kV Substation
Transmission owner
SHET
Technology
Hydro
Capacity (TEC)
75 MW
Agreement
Direct Connection
Status
Built
NESO project number
PRO-001541

Source