Enderby BESS
Enderby BESS is a storage project of 249.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Earl Shilton 400kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- EARL SHILTON ENERGY PARK LIMITED
- Connection site
- Earl Shilton 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 249.9 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Nov 2033
- NESO project number
- PRO-003872
Also at Earl Shilton 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Earl Shilton BESS | Storage | 500 |
| Enderby Farm | Storage, Solar | 200 |
| Enderby Farm 2 | Storage, Solar | 700 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.