EcoWymondley

EcoWymondley is a demand, storage, solar project of 249 MW in NESO's TEC Register of 23 Oct 2026, connecting at Wymondley 2 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Econergy International Limited
Connection site
Wymondley 2 400kV Substation
Transmission owner
NGET
Technology
Demand, Storage, Solar
Capacity (TEC)
249 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-002529

Also at Wymondley 2 400kV Substation

ProjectTechnologyMW
Wymondley GEC (Ethos Green)Storage, Solar700

Source