EcoMablethorpe

EcoMablethorpe is a storage, solar project of 249 MW in NESO's TEC Register of 23 Oct 2026, connecting at Mablethorpe 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Econergy International Limited
Connection site
Mablethorpe 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
249 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Aug 2034
NESO project number
PRO-002583

Also at Mablethorpe 400kV Substation

ProjectTechnologyMW
Mablethorpe Green Energy CentreDemand, Storage, Solar1,025