Ebstree Road BESS
Ebstree Road BESS is a storage project of 150 MW in NESO's TEC Register of 23 Oct 2026, connecting at Staffordshire Connection Node B 132kV Substation (NGET). Status: Scoping.
- Customer
- Voltwise Power Holdings Limited
- Connection site
- Staffordshire Connection Node B 132kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 150 MW
- Agreement
- Embedded
- Status
- Scoping
- MW effective from
- 30 Oct 2037
- NESO project number
- PRO-004679
Also at Staffordshire Connection Node B 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Orchard BESS | Storage | 100 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.