East Pit

East Pit is a storage, solar project of 750 MW in NESO's TEC Register of 23 Oct 2026, connecting at Rhigos 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
CS UK HOLDINGS III LIMITED
Connection site
Rhigos 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
750 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
15 Oct 2037
NESO project number
PRO-002736

Also at Rhigos 400kV Substation

ProjectTechnologyMW
Hirwaun Power StationGas299
Nant AmanOnshore wind143
Pen Y Cymoedd Wind FarmOnshore wind228
TarenniOnshore wind188