Grid GuardianOpen the evidence in the app

Dungeness Energy Park

Dungeness Energy Park is a storage, solar project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Dungeness 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
SOUTH KENT ENERGY PARK LIMITED
Connection site
Dungeness 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
500 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-001986

Also at Dungeness 400kV Substation

ProjectTechnologyMW
BLUE PLANET SOLARStorage, Solar500
Dungeness BNuclear0

Source