Drongan Battery Storage is a storage project of 100 MW in NESO's TEC Register of 23 Oct 2026, connecting at Coylton 275/132kV (SPT). Status: Scoping. Gate 1.
- Customer
- Drongan Battery Storage Ltd
- Connection site
- Coylton 275/132kV
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 100 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2027
- NESO project number
- PRO-002287
Also at Coylton 275/132kV
| Project | Technology | MW |
|---|---|---|
| Coylton 275kV Greener Grid Park | Storage | 50–450 |
| Coylton Farm | Storage | 300 |
| Hare Hill Extension Wind Farm | Onshore wind | 29.75 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.