Dougliehill BESS
Dougliehill BESS is a storage project of 49 MW in NESO's TEC Register of 23 Oct 2026, connecting at DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION (SPT). Status: Scoping. Gate 1.
- Customer
- Bluestone Energy Ltd
- Connection site
- DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 49 MW
- Agreement
- Embedded
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2026
- NESO project number
- PRO-002411
Also at DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION
| Project | Technology | MW |
|---|---|---|
| Devol Moor Battery & Solar Project | Storage | 400 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.