Grid GuardianOpen the evidence in the app

Dougliehill BESS

Dougliehill BESS is a storage project of 49 MW in NESO's TEC Register of 23 Oct 2026, connecting at DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION (SPT). Status: Scoping. Gate 1.

Customer
Bluestone Energy Ltd
Connection site
DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
49 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2026
NESO project number
PRO-002411

Also at DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION

ProjectTechnologyMW
Devol Moor Battery & Solar ProjectStorage400

Source