Derwent
Derwent is a chp (combined heat and power) project of 162 MW in NESO's TEC Register of 23 Oct 2026, connecting at Willington 132kV Substation (NGET). Status: Built.
- Customer
- UK UTILITY RESERVE LIMITED
- Connection site
- Willington 132kV Substation
- Transmission owner
- NGET
- Technology
- CHP (Combined Heat and Power)
- Capacity (TEC)
- 162 MW
- Agreement
- Embedded
- Status
- Built
- MW effective from
- 1 Apr 2024
- NESO project number
- PRO-000120
Also at Willington 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Trafalgar Park | Thermal | 14 |
| Willington | Storage, Solar | 600 |
| Willington Energy Park | Storage, Solar | 500 |
| Willington Green Energy Centre | Demand, Storage, Solar | 400–1,025 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.