Grid GuardianOpen the evidence in the app

Dealanach WLC WF

Dealanach WLC WF is a onshore wind project of 12 MW in NESO's TEC Register of 23 Oct 2026, connecting at Hopsrig Collector 132/33kV Substation (SPT). Status: Scoping.

Customer
DEALANACH LIMITED
Connection site
Hopsrig Collector 132/33kV Substation
Transmission owner
SPT
Technology
Onshore wind
Capacity (TEC)
12 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
15 Dec 2026
NESO project number
PRO-001722

Also at Hopsrig Collector 132/33kV Substation

ProjectTechnologyMW
Hareshaw Rig Wind FarmOnshore wind40
Hopsrig Wind FarmOnshore wind48
Loganhead WindfarmOnshore wind36

Source