Grid GuardianOpen the evidence in the app

Daviot Windfarm BEGA

Daviot Windfarm BEGA is a storage, onshore wind project of 45 MW in NESO's TEC Register of 23 Oct 2026, connecting at INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION (SHET). Status: Scoping. Gate 1.

Customer
Cubico UK Development Limited
Connection site
INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION
Transmission owner
SHET
Technology
Storage, Onshore wind
Capacity (TEC)
45 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2030
NESO project number
PRO-004874

Also at INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION

ProjectTechnologyMW
Moy Wind FarmOnshore wind60