Daines Green Energy Centre

Daines Green Energy Centre is a demand, storage, solar project of 480 MW in NESO's TEC Register of 23 Oct 2026, connecting at Daines 400kV Substation (NGET). Status: Scoping.

Customer
DAINES GREEN NG LIMITED
Connection site
Daines 400kV Substation
Transmission owner
NGET
Technology
Demand, Storage, Solar
Capacity (TEC)
480 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2030
NESO project number
PRO-001902

Also at Daines 400kV Substation

ProjectTechnologyMW
Carrington Lane BESSStorage1,800
Daines BESSStorage249.9
Daines BESSStorage600