Culachy Wind Farm
Culachy Wind Farm is a storage, onshore wind project of 115 MW in NESO's TEC Register of 23 Oct 2026, connecting at Fort Augustus 2 400kV Substation (SHET). Status: Scoping. Gate 1.
- Customer
- FRED OLSEN RENEWABLES LIMITED
- Connection site
- Fort Augustus 2 400kV Substation
- Transmission owner
- SHET
- Technology
- Storage, Onshore wind
- Capacity (TEC)
- 115 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2037
- NESO project number
- PRO-005184
Also at Fort Augustus 2 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Millennium East | Onshore wind | 49.9 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.