Crystal Rig IV Wind Farm
Crystal Rig IV Wind Farm is a onshore wind project of 48.2 MW in NESO's TEC Register of 23 Oct 2026, connecting at Crystal Rig 400kV substation (SPT). Status: Built.
- Customer
- CRYSTAL RIG IV LIMITED
- Connection site
- Crystal Rig 400kV substation
- Transmission owner
- SPT
- Technology
- Onshore wind
- Capacity (TEC)
- 48.2 MW
- Agreement
- Direct Connection
- Status
- Built
- NESO project number
- PRO-000520
Also at Crystal Rig 400kV substation
| Project | Technology | MW |
|---|---|---|
| Crystal Rig II Wind Farm | Onshore wind | 138 |
| Crystal Rig III Wind Farm | Onshore wind | 13.8 |
Source