Craigdarroch Hybrid Wind and BESS

Craigdarroch Hybrid Wind and BESS is a storage, onshore wind project of 159.2 MW in NESO's TEC Register of 23 Oct 2026, connecting at Craigdarroch Hybrid Wind & BESS 132kV Substation (SPT). Status: Scoping. Gate 1.

Customer
VOLTALIA UK LTD
Connection site
Craigdarroch Hybrid Wind & BESS 132kV Substation
Transmission owner
SPT
Technology
Storage, Onshore wind
Capacity (TEC)
159.2 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Jun 2037
NESO project number
PRO-005012