Cowley (Tertiary)

Cowley (Tertiary) is a storage, solar project of 57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Cowley 400kV Substation (NGET). Status: Scoping.

Customer
COWLEY BALDON GREEN LIMITED
Connection site
Cowley 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
57 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
14 Nov 2025
NESO project number
PRO-000407

Also at Cowley 400kV Substation

ProjectTechnologyMW
CowleyStorage49.9
Cowley Energy StorageStorage200–300
Cowley FarmStorage, Solar200
Cowley Farm 2Storage, Solar700
Green Frog at Lester WayGas12
Witney BESSStorage150