Cott's Farm

Cott's Farm is a storage, solar project of 100 MW in NESO's TEC Register of 23 Oct 2026, connecting at Cott's Farm 132kV Substation (SHET). Status: Scoping.

Customer
BORALEX LIMITED
Connection site
Cott's Farm 132kV Substation
Transmission owner
SHET
Technology
Storage, Solar
Capacity (TEC)
100 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2034
NESO project number
PRO-005017