Grid GuardianOpen the evidence in the app

Corriemoillie BESS

Corriemoillie BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Corriemoillie 132kV Substation (SHET). Status: Scoping. Gate 1.

Customer
FIELD CORRIEMOILLIE LTD
Connection site
Corriemoillie 132kV Substation
Transmission owner
SHET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Sept 2029
NESO project number
PRO-003992

Also at Corriemoillie 132kV Substation

ProjectTechnologyMW
Corriemoillie Wind FarmOnshore wind47.5
Isenau FourStorage200
LochluichartOnshore wind69