Grid GuardianOpen the evidence in the app

Church Road Farm

Church Road Farm is a storage project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at South Anglia Connection Node D 132kV Substation (NGET). Status: Scoping. Gate 1.

Customer
QAIR RENEWABLES UK LIMITED
Connection site
South Anglia Connection Node D 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
400 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2034
NESO project number
PRO-005074

Also at South Anglia Connection Node D 132kV Substation

ProjectTechnologyMW
Cambridgeshire Energy Storage CentreStorage, Pumped storage, Thermal500
SunnicaStorage, Solar500