Chesterfield
Chesterfield is a storage, solar project of 600 MW in NESO's TEC Register of 23 Oct 2026, connecting at Chesterfield 400kV Substation (Not yet constructed) (NGET). Status: Scoping. Gate 1.
- Customer
- SSE RENEWABLES SOLAR & BATTERY HOLDINGS LIMITED
- Connection site
- Chesterfield 400kV Substation (Not yet constructed)
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 600 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Oct 2032
- NESO project number
- PRO-003861
Also at Chesterfield 400kV Substation (Not yet constructed)
| Project | Technology | MW |
|---|---|---|
| Arkwright | Storage | 57 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.