Cellarhead Home Farm
Cellarhead Home Farm is a storage project of 280 MW in NESO's TEC Register of 23 Oct 2026, connecting at Cellarhead 132kV Substation (NGET). Status: Scoping.
- Customer
- CELLARHEAD BESS LTD
- Connection site
- Cellarhead 132kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 280 MW
- Agreement
- Embedded
- Status
- Scoping
- MW effective from
- 31 Oct 2028
- NESO project number
- PRO-001715
Also at Cellarhead 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Cellarhead | Storage, Solar | 400 |
| Cellarhead 400kV Energy Storage | Storage | 300 |
| Cellarhead Green Energy Centre | Storage, Solar | 400 |
| Chatterley | Gas | 20 |
| Thorney Edge | Storage | 300 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.