Castlemilk 1

Castlemilk 1 is a solar project of 300 MW in NESO's TEC Register of 23 Oct 2026, connecting at Castlemilk 400kV Substation (SPT). Status: Scoping.

Customer
Queequeg Renewables Ltd
Connection site
Castlemilk 400kV Substation
Transmission owner
SPT
Technology
Solar
Capacity (TEC)
300 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2036
NESO project number
PRO-003932