Cairn Duhie Wind Farm

Cairn Duhie Wind Farm is a onshore wind project of 67.2 MW in NESO's TEC Register of 23 Oct 2026, connecting at Berryburn 275/33kV GSP Substation (SHET). Status: Consents Approved. Gate 2.

Customer
Cairn Duhie Energy Limited
Connection site
Berryburn 275/33kV GSP Substation
Transmission owner
SHET
Technology
Onshore wind
Capacity (TEC)
67.2 MW
Agreement
Embedded
Gate
Gate 2
Status
Consents Approved
MW effective from
31 Oct 2028
NESO project number
PRO-001743

Also at Berryburn 275/33kV GSP Substation

ProjectTechnologyMW
Berryburn Extension Wind FarmOnshore wind43.2
Corshellach Battery Energy Storage SystemStorage49.9