Bushbury Green Energy Centre
Bushbury Green Energy Centre is a storage, solar project of 480 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bushbury 275kV Substation (NGET). Status: Scoping.
- Customer
- BUSHBURY GREEN NG LIMITED
- Connection site
- Bushbury 275kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 480 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 30 Oct 2028
- NESO project number
- PRO-001907
Source