Burwell (Tertiary)
Burwell (Tertiary) is a storage project of 57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Burwell Main 400kV Substation (NGET). Status: Awaiting Consents.
- Customer
- PIVOTED POWER LLP
- Connection site
- Burwell Main 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 57 MW
- Agreement
- Direct Connection
- Status
- Awaiting Consents
- MW effective from
- 30 Jun 2029
- NESO project number
- PRO-001109