Brinsworth

Brinsworth is a storage project of 600 MW in NESO's TEC Register of 23 Oct 2026, connecting at Brinsworth B 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
SSE RENEWABLES SOLAR & BATTERY HOLDINGS LIMITED
Connection site
Brinsworth B 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
600 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2032
NESO project number
PRO-003821