Grid GuardianOpen the evidence in the app

Brigton of Ruthven BESS

Brigton of Ruthven BESS is a storage project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Alyth 400kV Substation (SHET). Status: Scoping.

Customer
MORRIS LESLIE LIMITED
Connection site
Alyth 400kV Substation
Transmission owner
SHET
Technology
Storage
Capacity (TEC)
500 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-004937

Also at Alyth 400kV Substation

ProjectTechnologyMW
ALYTH ENERGY STORAGE AND SOLARStorage, Solar400
Glenmoy Wind Solar & BESSStorage, Solar, Onshore wind224
Knockton Wind FarmOnshore wind130.2

Source