Grid GuardianOpen the evidence in the app

Braegrundie Farm

Braegrundie Farm is a storage project of 95 MW in NESO's TEC Register of 23 Oct 2026, connecting at Braegrundie Farm 132kV Substation (SHET). Status: Awaiting Consents. Gate 1.

Customer
AEUK BATTERY PROJECT III LTD
Connection site
Braegrundie Farm 132kV Substation
Transmission owner
SHET
Technology
Storage
Capacity (TEC)
95 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Awaiting Consents
MW effective from
30 Jun 2030
NESO project number
PRO-004674

Source