Grid GuardianOpen the evidence in the app

Bolney BESS

Bolney BESS is a storage project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at DRAGON GREEN 400kV SUBSTATION (NGET). Status: Scoping. Gate 1.

Customer
CSE45 LIMITED
Connection site
DRAGON GREEN 400kV SUBSTATION
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
49.9 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
11 Sept 2037
NESO project number
PRO-004026

Also at DRAGON GREEN 400kV SUBSTATION

ProjectTechnologyMW
Bolney Farm 2Storage, Solar700