Bodelwyddan BESS and PV is a storage, solar project of 110 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bodelwyddan 400kV Substation (NGET). Status: Scoping.

Customer
Bodelwyddan Solar & Energy Storage Limited
Connection site
Bodelwyddan 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
110 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2029
NESO project number
PRO-001657

Also at Bodelwyddan 400kV Substation

ProjectTechnologyMW
Awel Y MorOffshore wind1,100
Moelfre Energy ParkStorage158.4
Mona Offshore Wind FarmOffshore wind1,500
St Asaph SSEStorage, Solar600