Blyth BESS
Blyth BESS is a storage project of 450 MW in NESO's TEC Register of 23 Oct 2026, connecting at Blyth 275kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- SSE RENEWABLES SOLAR & BATTERY HOLDINGS LIMITED
- Connection site
- Blyth 275kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 450 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2036
- NESO project number
- PRO-002817
Also at Blyth 275kV Substation
| Project | Technology | MW |
|---|---|---|
| Berwick Bank Offshore Wind Farm C | Offshore wind | 1,800 |
| Hope Battery Storage | Storage | 400 |
| Icewind Blyth | Offshore wind | 1,000 |
| Lynemouth Power Station | Bioenergy | 396 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.